INSTALLATION
REMEMBER!
Treatment plant installation should be performed by (or under the supervision of) an Authorized SOTRALENTZ Partner.
Work with professionals! We are at your disposal!
INVESTMENT PREPARATION:
Installation of each home treatment plant should be proceeded with:
- reconnaissance of land and water conditions on your lot,
- realization of environmental impact statement in the case of channelling sewage to a surface receiver or running a business activity,
- notify the appropriate local agency about the construction (Town Council or Office of District Authorities).
Assistance of an Authorized SOTRALENTZ Partner
will be indispensable at each of theses stages.
LOCATION OF DEVICES ON THE LOT:
EPURBLOC® should be placed as close as possible to the outlet of a sewer from the building – (max. 5 m) and equipped with a high ventilation system, letting out the gases produced in the oxygen-free fermentation process.

And these are the remaining principles:
- The distance of min. 150 cm must be kept between the diffusing drainage and the level of groundwater (the highest yearly),
- To provide oxygen conditions the drainage cannot be placed too deeply, and the whole installation should be equipped with appropriate low and high ventilation,
- EPURBLOC® must be placed shallowly (max. 60 cm ppt),
- The installation cannot be assembled on periodically flooded areas,
- The outflow of surface water in the direction from the devices has to be provided (ground levelling or water removal drainage).
In order to acquire more detailed information concerning designing, documentation arranging, realization and exploitation of SOTRALENTZ treatment plants, please contact the closest Authorized Partner or the Company office.